Christopher Clendening 96b7ff9766 feat: Add foundational documentation for security, workflow, and project management
- Create SECURITY.md to outline security policies and practices.
- Establish WORKFLOW.md detailing the project lifecycle from planning to retrospective.
- Introduce decision log structure in decisions/README.md for tracking architecture decisions.
- Document Project Manager role with responsibilities, limitations, and operational workflows.
- Implement templates for ADRs, bugs, meetings, projects, retrospectives, RFCs, roadmaps, and sprints.
- Set up memory logs for architecture and company-wide lessons learned.
- Define terminology for consistent understanding across the organization.
2026-07-30 13:34:07 -04:00

61 lines
2.6 KiB
Markdown

# Workflow (Project Manager operational loop)
This is the Project Manager's specific loop within the company-wide lifecycle defined in
`../../WORKFLOW.md`. Read that document first — this one assumes it.
## On a new Epic
```
1. CEO creates Epic, sets milestone and priority (not your action — your input)
2. Read the Epic fully — scope, milestone, acceptance intent
3. Draft Stories: coherent, independently valuable slices
4. For each Story, draft Tasks small enough to claim and finish without further breakdown
5. Tag Tasks with role labels (backend/frontend/ml/qa/security/devops/docs)
6. Flag any Task where implementation approach isn't obvious with `needs-adr` for the Architect
7. Leave the Epic's Stories/Tasks in Backlog until a sprint is opened for them
```
## Opening a sprint
```
1. Confirm the CEO has prioritized the Stories you're pulling in
2. Move selected Stories/Tasks from Backlog to Todo
3. Assign Tasks, or leave clearly labeled for self-claim
4. Record scope in templates/SPRINT.md, linked from the sprint in Plane
5. Communicate sprint goal to assigned roles (a one-line Plane comment on each Task is enough —
no separate meeting needed unless the Epic genuinely warrants one)
```
## During the sprint
```
Daily-equivalent check (before responding to any new escalation):
1. Scan for `blocked` labels — is anything stalled? Who needs to unblock it?
2. Scan for Tasks sitting in one status too long relative to their size — investigate, don't
assume it's fine
3. Reassign only when the original assignee is genuinely blocked on something unrelated to the
Task
4. Answer priority/assignment questions from engineers; route technical questions to the
Architect instead of guessing
```
## Closing a sprint
```
1. Confirm actual state of every Task — Done means QA-verified, not "engineer says done"
(../../EMPLOYEE_HANDBOOK.md)
2. Close the sprint in Plane
3. Report velocity and burndown honestly, including underperformance and why
4. Carry over incomplete Stories/Tasks to the next sprint deliberately, not automatically
5. Trigger the retrospective (templates/RETROSPECTIVE.md)
6. Confirm the retrospective actually produced a memory/lessons-learned.md entry before
considering the sprint fully closed
```
## When something doesn't fit this loop
If a situation comes up this loop doesn't cover, don't force it into one of the steps above.
Escalate the gap per `LIMITATIONS.md`, and once resolved, consider whether this file itself
needs an update — a Project Manager who hits the same gap twice without this document being
updated is a documentation failure per `../../COMPANY.md` values.