Files
Netherwarlord 8f246fabbc feat: add plugin framework with UI contributions and suite selection
- Implemented PluginBlocks component to render various plugin UI elements.
- Created SuitePicker for selecting test suites and questions.
- Introduced usePluginUI hook for managing plugin UI state and manifest.
- Developed DocsPage for comprehensive plugin framework documentation.
- Added PluginPage to render pages declared by plugins based on the current path.
2026-07-28 03:00:55 -04:00

23 lines
1.3 KiB
Plaintext

A team must complete the tasks below before a product ships. Durations are in working days. Assume unlimited parallel staffing.
A. Draft specification — 4 days — no prerequisites
B. Legal review — 6 days — requires A
C. Build prototype — 10 days — requires A
D. Order long-lead components — 15 days — requires A
E. Assemble unit — 3 days — requires C and D
F. Safety certification — 8 days — requires E and B
G. Write documentation — 5 days — requires C
H. Package and ship — 2 days — requires F and G
Answer all of the following, showing your work.
1. Compute the earliest start and earliest finish for every task. Present this as a table.
2. The minimum number of working days from project start to ship.
3. The critical path, written as a task sequence.
4. The slack (float) on task B and on task G.
5. If task D slips by 3 days, does the ship date move? By how much? Show why.
6. If instead task G slips by 3 days, does the ship date move? Explain the difference between this case and the previous one.
7. You may shorten exactly one task. Which one compresses the schedule most, and what becomes the new bottleneck once you do?
Then state one real-world assumption baked into "unlimited parallel staffing" that would change your answer if relaxed.